Modernization of 3 turbocompressors in a fertilizer plant

02/20/20 – At the end of October 2019, our teams completed a major modernization project involving 3 turbocompressors in a fertilizer production plant in Africa.

This modernization project was decided by the customer for the following reasons:

  • Hydraulic governors (PG-PL from Woodward) equipping turbocompressors with mechanical technologies, were coupled to a complex set of linkages before ultimately controlling the valves of the turbines; which resulted in a much longer reaction time.
  • This old speed control technology made it difficult to communicate with the control room, even though turbocompressors are critical machines for the process in place.
  • The modernization increases the level of machine safety since it made it possible to associate with control systems, auxiliary safety equipment thus complying with the API 612 & 670 standards, and a SIL3 classification.

Modernize to meet the various needs

  • Slow reaction of mechanical technologies (hydraulic governors) on turbocompressors
  • Lack of direct communication in the control room for ultra-fast reaction in critical applications
  • Compliance with safety standards and SIL-3 classification
  • Turbocompressor on which the installation was mounted (speed 5,400 rpm - pressure 4.5 bar)

    Turbocompressor after modernization
  • Turbocompressor control room with the 505D control system and the ProTech TPS overspeed protection system

    505D et ProTechTPS en salle de contrôle
  • Installation of the QuickTrip for the safety of the turbocompressor (trip block assembly to release the hydraulic pressure from the turbine inlet)

    Installation QuickTrip pour la sécurité du turbocompresseur
  • Installation of the VariStroke actuator

    montage de l'actionneur VariStroke de Woodward
Previous Previous Previous Next Next Next
1234

Thus, the entire project, including the installation plans, the equipment supply and the commissioning and start-up, was carried out under the supervision of the AWF teams.

The onsite installation work was carried out by the customer teams under the supervision of AWF.

Today, the 3 turbocompressors are each fitted with a Woodward set (new generation 505 D + VariStroke-GI + ProTech TPS + QuickTrip).

To date, the customer is satisfied with the system which perfectly meets their expectations:

  • flexible and accurate control,
  • equipment with the latest standards for installations based on turbomachines,
  • real-time monitoring of its processes.

Partager cet article
  • Share on Facebook
  • Share on X
  • Share on WhatsApp
  • Share on LinkedIn
  • Share by Mail

Contact us

Phone: +33 232 92 70 60

Use our contact form

Subscribe to our newsletter (in French)

AWF France © Copyright - All Rights Reserved.
  • Link to LinkedIn
  • Link to Youtube
Link to: Exceptional visit of Woodward’s management Link to: Exceptional visit of Woodward’s management Exceptional visit of Woodward’s management Link to: I&C Audit of 54 Gas Turbines Link to: I&C Audit of 54 Gas Turbines Powerturbine part of a FT8 gas turbine audited by AWFI&C Audit of 54 Gas Turbines
Scroll to top Scroll to top Scroll to top